§ 22-39. As-built drawings.  


Latest version.
  • (a)

    Upon completion of construction of all streets, utilities or other improvements, two (2) sets of complete as-built final plans, dated, signed and certified by the engineer in charge shall be filed with the city engineer showing all features as actually installed including materials, size, location, depth or elevation, numbers, ends of lines, connections, wyes, valves, storm sewer drains, inlets, and all other pertinent information.

    (b)

    A statement of the cost of all water and sewer lines, and the appurtenances thereto, which are dedicated therein, such statement of cost to be used by the city for the sole purpose of developing its fixed asset inventory.

    (c)

    One (1) certified copy of the as-built plans for the sanitary sewer system shall be filed with the department of natural resources by the developer, or engineer of record.